The Edgerton Village Council accepts a bid for the Business Alley East Project. Bryan Excavating got the job with a $191,923.15 bid. The project runs from Indiana Street, at U.S. 6, to Hull Street. It will include installing a new 12-inch storm sewer, replacing all storm sewer laterals and the installation of a new 8-inch water main. The existing main will be abandoned and crews remove and replace all existing asphalt paving. A big job.