Courthouse needs unforeseen work done, commission ok’s it

The courthouse renovations bill just went up by almost $15,000. Williams County Commissioners ok’d two more changes to the restoration plan. The first is to replace the entire decking in Level B of the clock tower and a quarter of Level C. That’s about $12,500. The second addition is to repair two vertical pipes that receive waste water from all the courthouse’s fixtures.