Icebreaker Can Proceed

A company can proceed with plans to build what will be the first freshwater offshore wind-powered electric-generation facility in North America, in Lake Erie off the coast of Cleveland, the Ohio Supreme Court ruled. At issue is the 2020 approval by the Ohio Power Siting Board of the project by Icebreaker Windpower, which proposed the six-turbine development about 10 miles north of the city. Residents sued to stop the project, arguing the siting board didn’t have enough evidence to determine the project’s environmental impact and that the project doesn’t serve the public interest as defined in Ohio law. The court ruled 6-1 that the board had multiple studies before it that found a low impact on birds and bats.

Check Also

Family of seven in Toledo looking for a new place to live after fire.

A family of seven is safe but looking for a new place to live after …