Transportation officials say…construction is set to begin, in both the northbound and southbound lanes of I-69…from U.S. 20, to the Indiana Michigan State Line. During the project there will be alternating lane closures in each direction. Work is scheduled to start on or after May 10 and is expected to be completed later this fall.