The Edgerton Village Council awards a bid for the completion of road and water main work on East and West Hull streets. The project has faced some problems along the way, as the initial engineering by Poggemeyer Design Group underestimated the transportation costs of materials by around $100,000. This resulted in two attempts to receive bids on the project, ending with no bids. After going back to the engineering, the project was estimated to cost around $799,000. Bryan Excavating was the only company to bid on the project.
Check Also
Bryan BPA adding two new positions.
Tuesday night, the Bryan Board of Public Affairs (BPA) approved adding two new positions in …